Mark scheme (whole question; this part is marked with the orange bar)

Examiner's comment
Most students could make a start on this question and started to rank the scores. A few didn’t know how to deal properly with the tied ranks, but many scored the first two 2 d method marks. Most went on to use their in the standard formula for Spearman’s rank correlation but a few realised that they should be using the product moment correlation coefficient (pmcc) formula on their ranks and usually went on to obtain the correct answer. A few simply used the pmcc formula on the scores but it was encouraging to see that only one or two students found their d 2 from the scores rather
Key points from the mark scheme and examiner's report
- tied ranks in both rows (P: 3.5, 3.5 and 6, 6, 6
- Q: 5.5, 5.5)
- with ties use the pmcc formula on the ranks: rs = 0.791
- using 1 − 6Σd²/(n(n² − 1)) gives 0.796 (3 of 4 marks)