D1.4.1 Modelling of a project by an activity network, from a precedence…

Section
D1.4 Critical path analysis
Level
AS & A level
Statement
Modelling of a project by an activity network, from a precedence table.
Guidance
Activity on arc will be used. The use of dummies is included.
Since 2018
13 parts, 45 marks · topic pages: Critical path analysis

Back to the checklist

June 2025 · AS Paper 2 (Decision 1) · Q2(a) 1 mark
2 Activity Immediately preceding activities A - B - C - B E A, B F B G B H C, D I G, H J E K E, F, I L G, H M G, H (a) Explain how you can deduce from the precedence table that at least one dummy will be needed when drawing the activity network. Your explanation should refer to specific activities. (1)
June 2025 · AS Paper 2 (Decision 1) · Q2(b) 5 marks
(b) Draw the activity network described in the precedence table, using activity on arc. Your activity network must contain the minimum number of dummies only. (5)
June 2024 · AS Paper 2 (Decision 1) · Q2(a) 3 marks
2. A company manages an awards evening. The table below lists the activities required to set up the room for the evening, and their immediately preceding activities. Each activity requires exactly one person. Activity Immediately preceding activities A ‑ B A C A C E C F B, D, E G E H B J H, F, G Figure 1 shows a partially completed activity network used to model the project. Each activity is represented by an arc. B A C Figure 1 (a) Add the remaining five activities to Diagram 1 in the answer book to complete the activity network, using exactly two dummies. (3)
June 2024 · Paper 3D (Decision 1) · Q6(a) 5 marks
6. The precedence table below shows the 12 activities required to complete a project. Activity Immediately preceding activities A – B – C – A E A, B, C F A, B, C G C H D, E I D, E J D, E K F, G, J L F, G (a) Draw the activity network described in the precedence table, using activity on arc. Your activity network must contain the minimum number of dummies only. (5)
June 2023 · AS Paper 2 (Decision 1) · Q2(a) 1 mark
2. D(7) A(6) G(5) I(2) E(8) B(10) H(9) L(5) J(6) K(9) C(7) F(11) Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number in brackets on each arc gives the time required, in hours, to complete the corresponding activity. The numbers in circles are the event numbers. Each activity requires one worker, and the project is to be completed in the shortest possible time. (a) Explain the significance of the dummy activity from event 3 to event 4 (1)
June 2023 · Paper 3D (Decision 1) · Q6(a) 5 marks
6. The precedence table below shows the twelve activities required to complete a project. Immediately preceding Activity activities A – B – C – A E A, B F D, E G A, B, C H F, G I D, E J D, E K F, G, I, J L I (a) Draw the activity network described in the precedence table, using activity on arc. Your activity network must contain the minimum number of dummies only. (5)
June 2022 · AS Paper 2 (Decision 1) · Q2(a) 5 marks
2. Activity Immediately preceding activities A – B – C – – E A F A, B, C G C H C I E J E, F, G K D, H (a) Draw the activity network described in the precedence table above, using activity on arc. Your activity network must contain the minimum number of dummies only. (5)
June 2022 · AS Paper 2 (Decision 1) · Q2(b) 1 mark
(b) Explain why it is necessary to draw a dummy from the end of activity A. (1)
Nov 2021 · Paper 3D (Decision 1) · Q7(b) 4 marks
The precedence table for the remaining 6 activities is given below. Activity Immediately preceding activities I D, E, G, H J D, E, G, H K E, G, H L I, J, K M J, K N J, K (b) Complete the activity network in the answer book for the project. Your completed activity network must contain only the minimum number of dummies. (4)
Oct 2020 · Paper 3D (Decision 1) · Q2(a) 2 marks
2. K(5) D(4) E(5) L(6) A(6) I(4) B(7) F(3) G(4) C(5) J(6) H(3) Figure 1 The network in Figure 1 shows the activities that need to be undertaken to complete a project. Each activity is represented by an arc and the duration, in hours, of the corresponding activity is shown in brackets. (a) Explain why each of the dummy activities is required. (2)
June 2019 · AS Paper 2 (Decision 1) · Q3(a) 5 marks
3. Activity Immediately preceding activities A - B - C A A E A F B, C G B, C H I D, E, F, G J D, E, F, G K G (a) Draw the activity network described in the precedence table above, using activity on arc. Your activity network must contain the minimum number of dummies. (5)
June 2019 · Paper 3D (Decision 1) · Q5(a) 5 marks
5. Activity Immediately preceding activities A – B – C – A E C F B, C, D G A H B, C, D I B, C, D, G J B, C, D, G K E, H (a) Draw the activity network described in the precedence table above, using activity on arc. Your activity network must contain only the minimum number of dummies. (5)
June 2018 · AS Paper 2 (Decision 1) · Q3(a) 3 marks
3. Time taken (days) Immediately preceding activities PAS as a eeee ee ee ee eee a ee ee ee: The table above shows the activities required for the completion of a building project. For each activity, the table shows the time it takes, in days, and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time. A(5) F(3) H(5) I(7) B(8) C(4) Figure 2 Figure 2 showsa partially completed activity network used to model the project. The activities are represented by the arcs and the number in brackets on each arc is the time taken, in days, to complete the corresponding activity. (a) Add the missing activities and necessary dummies to Diagram 1 in the answer book. (3)

Find an Edexcel Further Maths tutor

Stuck on this? Book a trial lesson with our Further Maths tutor.

Prefer email? Send an enquiry

If you are under 18, please include a parent's contact details. Enquiries go to enquiries@alevelfurthermathstutor.com and are deleted once handled.