D1.4.2 Completion of the precedence table for a given activity network.

Section
D1.4 Critical path analysis
Level
AS & A level
Statement
Completion of the precedence table for a given activity network.
Guidance
In a precedence network, precedence tables will only show immediate predecessors.
Since 2018
6 parts, 11 marks · topic pages: Critical path analysis

Back to the checklist

June 2025 · Paper 3D (Decision 1) · Q6(a) 2 marks
6. D(7) H(6) A(2) G(5) J(2) I(10) B(4) K(6) E(4) C(3) L(10) F(5) M(7) Figure 3 A project is modelled by the activity network shown in Figure 3. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, to complete the corresponding activity. The project is to be completed in the shortest possible time. (a) Complete Table 1 in the answer book to show the immediately preceding activities for each activity. (2)
June 2023 · AS Paper 2 (Decision 1) · Q2(a) 1 mark
2. D(7) A(6) G(5) I(2) E(8) B(10) H(9) L(5) J(6) K(9) C(7) F(11) Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number in brackets on each arc gives the time required, in hours, to complete the corresponding activity. The numbers in circles are the event numbers. Each activity requires one worker, and the project is to be completed in the shortest possible time. (a) Explain the significance of the dummy activity from event 3 to event 4 (1)
June 2022 · Paper 3D (Decision 1) · Q5(a) 2 marks
5. D(x) A(4) G(3) J(7) B(5) E(4) C(7) H(5) K(6) F(x) Figure 2 The network in Figure 2 shows the activities that need to be completed for a project. Each activity is represented by an arc and the duration of the activity, in days, is shown in brackets. The early event times are shown in Figure 2. (a) Complete Table 1 in the answer book to show the immediately preceding activities for each activity. (2)
Nov 2021 · Paper 3D (Decision 1) · Q7(a) 2 marks
7. A F B E G C H Figure 5 Figure 5 shows a partially completed activity network for a project that consists of 14 activities. (a) Complete the precedence table in the answer book for the 8 activities in Figure 5. (2)
Oct 2020 · AS Paper 2 (Decision 1) · Q2(a) 2 marks
2. D(6) E(8) I(8) A(5) B(3) F(5) J(9) C(4) G(3) K(6) H(7) Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, to complete the corresponding activity. Each activity requires one worker. The project is to be completed in the shortest possible time. (a) Complete the precedence table in the answer book. (2)
Oct 2020 · Paper 3D (Decision 1) · Q2(b) 2 marks
(b) Complete the table in the answer book to show the immediately preceding activities for each activity. (2)

Find an Edexcel Further Maths tutor

Stuck on this? Book a trial lesson with our Further Maths tutor.

Prefer email? Send an enquiry

If you are under 18, please include a parent's contact details. Enquiries go to enquiries@alevelfurthermathstutor.com and are deleted once handled.