D1.4.4 Calculation of the total float of an activity. Construction of…

Section
D1.4 Critical path analysis
Level
AS & A level
Statement
Calculation of the total float of an activity. Construction of Gantt (cascade) charts.
Guidance
Each activity will require only one worker.
Since 2018
18 parts, 43 marks · topic pages: Critical path analysis

Back to the checklist

June 2025 · AS Paper 2 (Decision 1) · Q2(d) 1 mark
One of the activities now needs to be chosen to be extended by an hour. When the change is made the minimum completion time must not be affected. (d) List the activities that could be chosen. (1)
June 2025 · Paper 3D (Decision 1) · Q6(c) 4 marks
(c) Draw a Gantt chart for this project on Grid 1 in the answer book. (4)
June 2024 · AS Paper 2 (Decision 1) · Q2(d) 1 mark
(d) Given that the main courses need to be ready to be served (with all activities completed) at 8 pm, state the latest time that activity R can start. (1)
June 2024 · Paper 3D (Decision 1) · Q6(b) 4 marks
Each of the activities shown in the precedence table requires one worker. The project is to be completed in the minimum possible time. 12 13 14 15 16 17 18 19 20 C E J K A G H I B F L Figure 3 Figure 3 shows a schedule for the project using three workers. (b) (i) State the critical path for the network. (ii) State the minimum completion time for the project. (iii) Calculate the total float on activity B. (iv) Calculate the total float on activity G. (4)
June 2024 · Paper 3D (Decision 1) · Q6(c) 2 marks
Immediately after the start of the project, it is found that the duration of activity I, as shown in Figure 3, is incorrect. In fact, activity I will take 8 hours. The durations of all the other activities remain as shown in Figure 3. (c) Determine whether the project can still be completed in the minimum completion time using only three workers when the duration of activity I is 8 hours. Your answer must make specific reference to workers, times and activities. (2)
June 2023 · AS Paper 2 (Decision 1) · Q2(e) 4 marks
(e) Draw a Gantt chart for this project on Grid 1 in the answer book. (4)
June 2023 · Paper 3D (Decision 1) · Q6(c) 1 mark
Given that the total float of activity F is 2 hours, (c) state the duration of activity F. (1)
June 2023 · Paper 3D (Decision 1) · Q6(d) 2 marks
The duration of activity J is x hours, and the duration of activity K is y hours, where x > 0 and y > 0 (d) (i) State, in terms of y, the maximum possible total float for activity K. (ii) State, in terms of x and y, the total float for activity J. (2)
June 2022 · Paper 3D (Decision 1) · Q5(d) 1 mark
(d) Calculate the total float for activity G. (1)
June 2022 · Paper 3D (Decision 1) · Q5(f) 5 marks
(f) Draw a Gantt chart on Grid 1 in the answer book to represent the activity network. (5)
Nov 2021 · Paper 3D (Decision 1) · Q2(c) 3 marks
(c) Schedule the activities using Grid 1 in the answer book. (3)
Oct 2020 · AS Paper 2 (Decision 1) · Q2(d) 1 mark
(d) Calculate the maximum number of hours by which activity H could be delayed without affecting the shortest possible completion time of the project. You must make the numbers used in your calculation clear. (1)
Oct 2020 · AS Paper 2 (Decision 1) · Q2(f) 3 marks
(f) Draw a cascade chart for this project on Grid 1 in the answer book. (3)
Oct 2020 · AS Paper 2 (Decision 1) · Q2(g) 1 mark
(g) Using the answer to (f), explain why it is not possible to complete the project in the shortest possible time using the number of workers found in (e). (1)
Oct 2020 · Paper 3D (Decision 1) · Q2(e) 2 marks
(e) Determine whether or not the project can be completed in the minimum possible time using fewer workers than the number indicated by the resource histogram in (d). You must justify your answer with reference to the resource histogram and the completed Diagram 1. (2)
June 2019 · Paper 3D (Decision 1) · Q4(a) 2 marks
4. D(11) I(6) E(5) A(8) J(4) K(6) B(6) F(8) L(7) Key: G(10) Early M(6) C(7) event time Late event H(x) time Figure 3 The network in Figure 3 shows the activities that need to be undertaken to complete a project. Each activity is represented by an arc and the duration of the activity, in days, is shown in brackets. The early event times and late event times are to be shown at each vertex and one late event time has been completed for you. The total float of activity H is 7 days. (a) Explain, with detailed reasoning, why x = 11 (2)
June 2019 · Paper 3D (Decision 1) · Q4(d) 3 marks
(d) Schedule the activities using Grid 1 in the answer book. (3)
June 2018 · AS Paper 2 (Decision 1) · Q3(d) 3 marks
At the beginning of the project it is decided that activity G is no longer required. (d) Explain what effect, if any, this will have on (i) the shortest completion time of the project if activity G is no longer required, (ii) the timing of the remaining activities. (3)

Find an Edexcel Further Maths tutor

Stuck on this? Book a trial lesson with our Further Maths tutor.

Prefer email? Send an enquiry

If you are under 18, please include a parent's contact details. Enquiries go to enquiries@alevelfurthermathstutor.com and are deleted once handled.