Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
The first two parts of this question were very standard definitions and procedures and therefore very accessible to all learners, however the advanced understanding required for the final two parts were able to clearly discriminate between learners who could follow procedure and those at the higher end of the scoring scale who really understood it. Part a) was generally well answered with a majority of learners scoring this mark for a correct explanation. The most common non-scoring response was to only consider the dependency of E on A and B, which was not acceptable in the context of the whole network. Those attempting to use the unique argument sometimes failed to mention both the start and end notes, and a loss of the B mark in this question was often due to lack of accuracy rather than a wrong idea. Part b) was generally very well drawn overall, with a large number of responses scoring full marks. The most common error was to share the same start and end node for L and M, thus losing the last two marks, otherwise learners handled the network well (though some of the responses were not user-friendly to navigate. A small number of activity-on-node responses were attempted; learners should be aware that this scores no marks. A few did not have a single start node, which also scored no marks. Lack of arrows on the dummies caused some to gain only the M mark. A more common error tended to be either the lack of Activity J, or additional activities when the candidate’s lines were not long enough or they used additional dummies. Part c) was answered correctly on approximately half of the scripts. It was still well attempted, however a full range of multiples of 3 seen from 9 to 39 which demonstrated a lack of understanding of this particular application. Part d) was only answered correctly by the most able learners. Those that did get 15 generally found at least some of the non-critical activities, often listing only a small number of the required list. Those that first identified the critical path generally found the full set.
Key points from the mark scheme and examiner's report
activities with float of at least 1 hour, i.e. all non-critical: A, C, E, F, G, J, L, M
easiest after finding the critical path B, D, H, I, K
June 2025 · Paper 3D (Decision 1) · Q6(c)4 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
In part (c) the Gantt chart was also completed well and better than in previous series. Only a small number of candidates submitted no response, and most mistakes stemmed from errors in part (b) that carried forward. Very few attempted a scheduling diagram, and most followed the standard format. Overall, this was one of the strongest parts of the question.
Key points from the mark scheme and examiner's report
cascade chart: critical C, E, G, H, J on top row
non-critical activities at earliest start with floats shaded (e.g. K float 7, M float 5)
a scheduling diagram scores 0
June 2024 · AS Paper 2 (Decision 1) · Q2(d)1 mark
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
This was generally a high-scoring question, with the vast majority of candidates scoring at least 6 out of a possible 8 marks. Part a) was a relatively straightforward network, with the additional scaffold of a partially drawn network. Whilst the significant majority of candidates scored full marks, a surprising number lost the last accuracy mark for omitting activity J. Despite the network being given, several candidates still attempted to put activities on nodes. However fewer candidates lost marks for missing arrows, or additional dummies. Part b) was again well-answered with the majority scoring 2 or 3 marks. The most frequent errors were in the late times for U (29), M (38) and N (49, leading to a rogue value here) but mistakes were exceptionally rare in the forward pass. In part c) the majority of candidates correctly identified the critical activities, although activity P was included by some. Part d) caused issues for less secure candidates; some obtained 7:27pm (subtracting 33 minutes from 8pm), many achieved 7:29pm and 7:31pm or 7:34pm following numerical errors or misusing the 4 minutes of float. A surprising number seemed to misinterpret the question and gave answers beyond 8pm. Others correctly identified 33 minutes but then failed to add the pm for the correct time or gave a time of 8.33pm. This served as a reasonable discriminator mark for stronger candidates.
Key points from the mark scheme and examiner's report
project starts at 7 pm (60 minutes before 8 pm)
R must start by 48 − 15 = 33 minutes, so 7:33 pm (pm needed)
7:27 pm, 7:29 pm and 8:33 pm were common errors
June 2024 · Paper 3D (Decision 1) · Q6(b)4 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
Overall, this question was very accessible with at least the first three marks in part (a) and the first mark in part (b) gained by most candidates. In part (b) nearly all candidates gained the first mark for the correct critical path, CEJK, with many also gaining the mark for the correct minimum completion time of 20 hours. A significant number of candidates calculated the correct float on Activity B of 2 hours, but It was rare to see a correct calculation for the total float on Activity G. Many candidates gave the float incorrectly as 0 (zero stated or 12 – 8 – 4 due to H starting immediately after G on the given scheduling diagram) or as 1 (as G depends on C which finishes at 7 but G starts at 8 on scheduling diagram).
Key points from the mark scheme and examiner's report
critical path C–E–J–K, 20 hours
float on B = 2
float on G = 15 − 7 − 4 = 4 (K must start by 15
use the network, not the schedule)
many gave 0 or 1 for G from the schedule
June 2024 · Paper 3D (Decision 1) · Q6(c)2 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
Overall, this question was very accessible with at least the first three marks in part (a) and the first mark in part (b) gained by most candidates. In part (c) few candidates earned both marks by giving the complete detail required, expressing for example that: Activity I could be done by Worker 2, starting at 12 hours (and finishing at 20) and Activity H could then be done by Worker 3 from 15 hours (to 17) hours. Many candidates had the right idea but did not actually write enough detail, for example by not mentioning specific timings. Several candidates thought that it was not possible to complete without a further worker or completing after 22 hours or splitting the activity between two workers.
Key points from the mark scheme and examiner's report
yes: worker 3 does I from 12 to 20 and worker 2 does H then L between 12 and 20 (L starting by 17)
must give workers, times and activities
June 2023 · AS Paper 2 (Decision 1) · Q2(e)4 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
drawing of the cascade chart in part (e) was done well by most candidates with the majority using the standard approach of placing the critical activities on a single line at the top of the chart and then placing each non-critical activity on a separate line with their corresponding float, usually shaded or shown in a way to differentiate from the duration, appearing after. Very few scheduling diagrams were seen (which are not on spec. anyway) and the most common error was to either forgot one (or more) activities or have an incorrect duration/float on one or more activities.
Key points from the mark scheme and examiner's report
critical activities A, E, J, K on one line
each non-critical activity on its own line followed by its total float
scheduling diagrams with no floats score M0
omitted activities and wrong floats were the usual errors
June 2023 · Paper 3D (Decision 1) · Q6(c)1 mark
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
Part (b) was answered correctly in all but a small handful of responses. Part (c) by contrast was far more of a challenge and was frequently left blank. Many candidates were unsuccessful in identifying the relevant values for the window in which activity F could occur, with many incorrectly assuming the latest F could finish was at time 16. The most common incorrect duration stated was ‘2’ which was probably more common than the correct value of ‘4’.
Key points from the mark scheme and examiner's report
F can start at 12 and must finish by 18 (start of H), so 18 − 12 − 2 = 4 hours
2 was a common wrong answer
June 2023 · Paper 3D (Decision 1) · Q6(d)2 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
Part (d) was not answered well by many candidates and proved to be a good discriminator. There was confusion evident in both parts with incorrect values being used in many cases. For the float of activity K, a reasonable number of candidates correctly identified the interval 19 – 24 and knew that this interval was shared between the float and activity length. A common error was assuming that the length of activity J influenced this in the stated maximum case, despite the question stating that it should be in terms of 𝑦. For the float of J, few candidates identified the correct interval from 12 – 24, with a common error using the earliest finish time of activity D or the end of activity I. Other incorrect answers involved incorrectly using the float of activity K rather than the duration of K e.g. 24 -12 -𝑥-(5 -𝑦).
Key points from the mark scheme and examiner's report
K sits in the window 19–24: maximum float 5 − y
J from 12 to the start of K at 24 − y: float 12 − x − y
good discriminator
June 2022 · Paper 3D (Decision 1) · Q5(d)1 mark
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
Most candidates stated the correct critical activities and the value of the float for G in (d). Virtually all candidates extracted the required number of workers from the resource histogram and completed the table correctly in (e).
Key points from the mark scheme and examiner's report
total float of G = 15 − 11 − 3 = 1
June 2022 · Paper 3D (Decision 1) · Q5(f)5 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
In (f) most candidates attempted to draw a Gantt Chart, although some did not attempt this, and a small number drew a scheduling diagram instead. Those candidates who attempted the Gantt Chart drew the critical activities correctly and most also drew activities B, G and J correctly. Some candidates explicitly stated the value of x and then went on to draw D and F correctly and others implied the correct value of x from D and F shown on their Gantt Chart. A significant number of candidates made errors with the float for activity A.
Key points from the mark scheme and examiner's report
deduce x = 6 from the histogram (D and F end by time 10 and 13)
cascade chart with floats shown
critical C, E, H, K
errors mostly on A's float
a scheduling diagram scores 0
Nov 2021 · Paper 3D (Decision 1) · Q2(c)3 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
This was a standard question on critical path analysis and was a good source of marks for most of the candidates. The main issues seen were in part (c) in which some candidates’ schedules contained either 3 or 5 workers (rather than the correct number of 4). Candidates are reminded to check the duration, time-interval, and immediately preceding activities for each activity very carefully when constructing a schedule of the workers to activities.
Key points from the mark scheme and examiner's report
4 workers, not 3 or 5
check every activity's duration, time interval and immediate predecessors
not a cascade chart
Oct 2020 · AS Paper 2 (Decision 1) · Q2(d)1 mark
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
This question on critical path analysis was answered extremely well by many candidates. Part (d) required candidates to calculate the maximum number of hours by which activity H could be delayed without affecting the shortest possible completion time of the project and nearly all candidates realised that this calculation was equivalent to the total float for activity H and therefore was extremely well answered.
Key points from the mark scheme and examiner's report
total float of H = 13 − 5 − 7 = 1 hour
all three numbers must be seen
Oct 2020 · AS Paper 2 (Decision 1) · Q2(f)3 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
This question on critical path analysis was answered extremely well by many candidates. Most candidates in part (f) were well-versed in how to construct a cascade chart and examiners saw very few scheduling diagrams. Most floats were drawn in the standard way (as shown in previous mark schemes) and critical activities were almost always seen drawn along the top of the cascade chart although this was not always the case. Cascade charts were usually completed accurately and neatly with most errors occurring following through from errors in (b). From
Key points from the mark scheme and examiner's report
critical activities A, E, J along the top
non-critical activities at earliest start with floats shown
errors followed from (b)
occasional mis-plotting of I and K
Oct 2020 · AS Paper 2 (Decision 1) · Q2(g)1 mark
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
This question on critical path analysis was answered extremely well by many candidates. Part (g) required the candidates to explain why it was not possible to complete the project in the shortest possible time using the number of workers found in part (e). The most common
Key points from the mark scheme and examiner's report
at time 8.5 activities D, E, F and H must all be happening, so 3 workers is not enough
must refer to a specific time and the activities
Oct 2020 · Paper 3D (Decision 1) · Q2(e)2 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
was apparent that candidates had difficulty interpreting their histogram for (e). A number of candidates managed partial answers involving reduction from five workers to four by delaying D, G or H to time 10 or beyond, but it was very rare to see a complete correct answer.
Key points from the mark scheme and examiner's report
yes: delay a non-critical activity (e.g. H to start at 10, then J to 15) using its float
delaying F fails
complete answers were very rare
June 2019 · Paper 3D (Decision 1) · Q4(a)2 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
In part (a) very few candidates explained, with detailed reasoning, why x = 11. For the first mark candidates had to give a correct reason why the total float on activity H was given by 25 – 7 – x (e.g. mention that the early event time at the end of activity C is 7) and for the second mark (which was dependent on the first) a reason why the expression 25 – 7 – x leads to the given answer. Far too many candidates gave no reasoning at all and simply wrote down the equation 25 – 7 – x = 7 and then stated that x = 11.
Key points from the mark scheme and examiner's report
early event time at the end of C is 7, so float on H = 25 − 7 − x = 7 gives x = 11
must explain where 25 − 7 − x comes from
many just wrote the equation
June 2019 · Paper 3D (Decision 1) · Q4(d)3 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
Most candidates did attempt to produce a schedule in part (d). However, a significant proportion of candidates tried to construct a schedule with only three workers (possibly due to their answer for part (c)), therefore scoring only one mark and completely disregarding the significance of the Immediately Preceding Activities (IPA). Of those candidates who did have four workers in their schedule, a pleasing number were correct, though errors were sometimes seen in either the duration, time interval or IPA for one or more activities. It was pleasing to note that cascade charts were rarely seen.
Key points from the mark scheme and examiner's report
4 workers needed despite the bound of 3
check every activity's duration, time interval and immediate predecessors
not a cascade chart
many forced 3 workers and ignored precedences
June 2018 · AS Paper 2 (Decision 1) · Q3(d)3 marks
Mark scheme (whole question; this part is marked with the orange bar)
Examiner's comment
In (d)(i), most students were able to recognise that the removal of activity G would have no effect on the shortest completion time. Although some did state that it would be reduced. Similarly, for (d)(ii), the question asked for a comment on the timings of the remaining activities – so to gain both marks here, students needed to mention both that activity C was the only affected activity, and also that the timing of this activity would now be adjusted to finish at time 16 (or start as late as time 12).
Key points from the mark scheme and examiner's report
(i) no effect as G is not critical
(ii) only C is affected: it can now start at 12 or finish as late as 16
many omitted a relevant time