D1.4.6 Scheduling the activities using the least number of workers…

Section
D1.4 Critical path analysis
Level
A level only
Statement
Scheduling the activities using the least number of workers required to complete the project.
Since 2018
3 parts, 8 marks · topic pages: Critical path analysis

Back to the checklist

June 2024 · Paper 3D (Decision 1) · Q6(c) 2 marks
Immediately after the start of the project, it is found that the duration of activity I, as shown in Figure 3, is incorrect. In fact, activity I will take 8 hours. The durations of all the other activities remain as shown in Figure 3. (c) Determine whether the project can still be completed in the minimum completion time using only three workers when the duration of activity I is 8 hours. Your answer must make specific reference to workers, times and activities. (2)
Nov 2021 · Paper 3D (Decision 1) · Q2(c) 3 marks
(c) Schedule the activities using Grid 1 in the answer book. (3)
June 2019 · Paper 3D (Decision 1) · Q4(d) 3 marks
(d) Schedule the activities using Grid 1 in the answer book. (3)

Find an Edexcel Further Maths tutor

Stuck on this? Book a trial lesson with our Further Maths tutor.

Prefer email? Send an enquiry

If you are under 18, please include a parent's contact details. Enquiries go to enquiries@alevelfurthermathstutor.com and are deleted once handled.